Installation and Commissioning of Mechanical & Electrical Part of Vietnam Khe Bo Hydropower Station’s 2X50MW Unit Covered by No. 23 Contract Section Completed
Release date:2013-09-28 source:原創(chuàng) browse:2821
Browse and share:

The 72 hours’ test-run of No.2 unit of the mechanical and electrical part of Vietnam Khe Bo Hydropower Station covered by No. 23 contract section general contacted through the way of EPC by UREC has been smoothly completed by 20:00 on the date of 27 August, 2013. Up to now, the installation and commissioning of mechanical & electrical part of Vietnam Khe Bo Hydropower Station’s 2X50MW unit covered by No. 23 contract section has been fulfilled perfectly! 